The Heartland corridor · what changed while you were away

Tracked projects
376
194 active · 39 states
Capital in motion
$1.2T
Across corridor
Power demand
77.5 GW
Planned load
Pipeline value
$6.0B
159 scored opportunities
Fresh activity
45
Rumored + announced
States covered
39
Heartland-led

Live event feed

Permits, interconnection filings, procurement and hiring updates

136 updates
Staffing ramp postedHiring+2 evidence

New operating and technician roles posted for Great Lakes Flint Colocation Facility.

Great Lakes Flint Colocation FacilitytodayLocal reporting / county records
Staffing ramp postedHiring+2 evidence

New operating and technician roles posted for Great Lakes Cleveland Carrier Hotel.

Great Lakes Cleveland Carrier HoteltodayLocal reporting / county records
Building permit filedPermit+2 evidence

County permitting records show progress on Continuum Madison Data Center.

Continuum Madison Data Center3d agoLocal reporting / county records
Tool-install trades postingsHiring+3 evidence

New mechanical and electrical tool-install roles posted as fit-out prep continues on the New Albany site.

Intel Ohio One, Silicon Heartland5d agoJob board aggregation
Building permit activityPermit+4 evidence

County records show fresh permit activity on additional buildings in the campus footprint.

New Albany North Hyperscale Campus6d agoLocal reporting / county records
Interconnection study updateUtility+5 evidence

Load-study milestone advanced in the regional interconnection queue for the Piketon site.

PORTS Technology Campus, Piketon6d agoRTO queue
Staffing ramp postedHiring+2 evidence

New operating and technician roles posted for Digital Realty Franklin Park Campus.

Digital Realty Franklin Park Campus6d agoLocal reporting / county records
Sitework procurement openedProcurement+4 evidence

Early sitework and civil scopes appeared for bid on the Joliet campus.

Joliet Technology Center7d agoLocal reporting / county records
Staffing ramp postedHiring+2 evidence

New operating and technician roles posted for Involta Davenport Data Center.

Involta Davenport Data Center9d agoLocal reporting / county records
Large interconnection requestUtility+6 evidence

A 750MW load request appeared under a shell LLC in the AEP queue.

Project Coppertop (unconfirmed)12d agoPJM queue
Staffing ramp postedHiring+2 evidence

New operating and technician roles posted for Iron Mountain Underground Data Center.

Iron Mountain Underground Data Center12d agoLocal reporting / county records
Substation energization scheduledUtility+6 evidence

AEP Ohio filed a switching plan to energize the campus 138kV tie in Q4.

New Albany North Hyperscale Campus13d agoAEP Ohio filing