Stafford, Stafford County, VA38.422, -77.408

Vantage VA4 Campus

PermittingData Center

Vantage Data Centers

Stafford, Stafford County, VA

Verification80/100

How corroborated this project is, 0 to 100, built from primary evidence: permits, utility interconnection filings, procurement notices and hiring activity. Higher means more independent sources confirm it.

Vantage’s fourth Virginia campus: a $2 billion, 192 MW, three-building development on 82 acres in Stafford County, with the first building scheduled to open in late 2027 (Vantage Data Centers).

Investment$2B
Power demand192 MW
Jobs·
Serving utilityDominion Energy

Development stage

  1. Site Selection
  2. Pre-Construction
  3. Permitting
  4. Construction

Project timeline

Every detected update, newest first

No events recorded yet.

Procurement opportunities

Paid plan

  • No opportunities detected yet.