New Carlisle, St. Joseph County, IN41.709, -86.494

Project Everett (AWS New Carlisle)

OperationalData Center

Amazon Web Services

New Carlisle, St. Joseph County, IN

Verification92/100

How corroborated this project is, 0 to 100, built from primary evidence: permits, utility interconnection filings, procurement notices and hiring activity. Higher means more independent sources confirm it.

Amazon's "Project Rainier" campus, announced April 2024 as an $11 billion, largest-in-state-history Indiana commitment (Gov. Holcomb / IEDC). Designed for 2.2GW across up to 30 buildings, seven were online and the site fully operational by October 2025, running Trainium chips to train Anthropic's Claude models. Amazon has since layered on an additional $15 billion for further northern-Indiana sites.

Investment$11B
Power demand2,200 MW
Jobs1,000
Serving utilityAEP Indiana Michigan

Development stage

  1. Site Selection
  2. Pre-Construction
  3. Permitting
  4. Construction

Project timeline

Every detected update, newest first

  1. Dedicated generation studyUtility+6 evidence

    Interconnection and dedicated-generation studies advanced for the multi-GW complex.

    Jul 9, 2026PJM / MISO queue
  2. First building permits issuedPermit+4 evidence

    St. Joseph County issued foundation permits for the initial data halls.

    May 11, 2026County permits
  3. All 16 buildings under constructionAnnouncement+4 evidence

    AWS reported all 16 planned New Carlisle buildings under construction, targeting ~1GW online by Q3 2026.

    May 11, 2026Trade analysis
  4. $11B Indiana commitmentFinancing+5 evidence

    Amazon confirmed its largest single-state investment anchored here.

    Apr 25, 2026Corporate release

Procurement opportunities

3 tracked

  • Long-lead transformer & switchgear supply89
    Supplier / OEM$210M72% procure
    Window closes Feb 1, 2027
  • Mass earthwork & civil EPC85
    Construction$180M70% procure
    Window closes Nov 30, 2026
  • Electrical EPC subcontract package82
    Construction$95M65% procure
    Window closes Nov 30, 2026