New Albany North Hyperscale Campus
Under ConstructionData CenterAmazon Web Services
New Albany, Licking County, OH
How corroborated this project is, 0 to 100, built from primary evidence: permits, utility interconnection filings, procurement notices and hiring activity. Higher means more independent sources confirm it.
Five-building hyperscale campus, the first community confirmed under AWS's $7.8 billion June 2023 Central Ohio expansion pledge (part of a cumulative Ohio commitment AWS says will top $23 billion by 2030). Steel is up on the first two data halls, interconnection and substation work is the pacing item, and the campus carries roughly 105 full-time operating jobs once staffed.
Development stage
- Site Selection
- Pre-Construction
- Permitting
- Construction
Project timeline
Every detected update, newest first
- Building permit activityPermit+4 evidence
County records show fresh permit activity on additional buildings in the campus footprint.
Jul 18, 2026Local reporting / county records - Substation energization scheduledUtility+6 evidence
AEP Ohio filed a switching plan to energize the campus 138kV tie in Q4.
Jul 11, 2026AEP Ohio filing - Facilities staffing rampHiring+4 evidence
40+ data center technician and critical-facilities roles posted for the campus.
Jun 27, 2026Job board aggregation - Ohio data-center ballot ban fails to qualifyAnnouncement+3 evidence
A proposed constitutional amendment to ban data centers fell far short of signatures and will not appear on the November 2026 ballot, removing a policy overhang.
Jun 19, 2026Ohio Capital Journal - Data hall 3 building permitPermit+3 evidence
Licking County issued a foundation permit for the third data hall.
May 14, 2026Licking County permits - Chilled-water plant RFPProcurement+2 evidence
Mechanical contractor prequalification opened for the central utility plant.
Mar 30, 2026Procurement notice
Procurement opportunities
5 tracked
- Liquid cooling / CDU supply94Cooling$120M78% procureWindow closes Sep 15, 2026
- Power & thermal management OEM supply90Supplier / OEM$160M74% procureWindow closes Oct 10, 2026
- Medium-voltage switchgear88Power$85M72% procureWindow closes Aug 30, 2026
- Critical-facilities technician staffing87Staffing$18M80% procureWindow closes Sep 30, 2026
- Structured cabling & fiber76Networking$30M64% procureWindow closes Sep 30, 2026