TSMC Arizona Fabs (North Phoenix)
Under ConstructionManufacturingTSMC
Phoenix, Maricopa County, AZ
Verification90/100
How corroborated this project is, 0 to 100, built from primary evidence: permits, utility interconnection filings, procurement notices and hiring activity. Higher means more independent sources confirm it.
TSMC's north Phoenix semiconductor site is the largest greenfield foreign direct investment in US history, with total announced investment reaching $165B for six fabs plus advanced packaging and an R&D center. The third fab broke ground in April 2025 for N2/A16 nodes; the fabs are expected to create about 6,000 direct high-tech jobs and over 20,000 construction jobs.
Investment$165B
Power demand200 MW
Jobs6,000
Serving utilityArizona Public Service
Development stage
- Site Selection
- Pre-Construction
- Permitting
- Construction
Project timeline
Every detected update, newest first
No events recorded yet.
Procurement opportunities
0 tracked