Toyota Buffalo Hybrid Transaxle Plant

Under ConstructionManufacturing

Toyota Motor Corporation

Buffalo, Putnam County, WV

Verification74/100

How corroborated this project is, 0 to 100, built from primary evidence: permits, utility interconnection filings, procurement notices and hiring activity. Higher means more independent sources confirm it.

Toyota Motor Manufacturing West Virginia in Buffalo, Putnam County, confirmed a $210 million investment to add hybrid-transaxle production supporting Toyota's Kentucky and Indiana hybrid-vehicle lines, creating about 100 new jobs alongside the plant's existing engine production.

Investment$210M
Power demand·
Jobs100
Serving utilityAppalachian Power

Development stage

  1. Site Selection
  2. Pre-Construction
  3. Permitting
  4. Construction

Project timeline

Every detected update, newest first

  1. Local procurement notice filedProcurement+3 evidence

    Local trade press flagged a procurement notice tied to Toyota Buffalo Hybrid Transaxle Plant.

    Jun 11, 2026Local reporting / county records
  2. Building permit filedPermit+2 evidence

    County permitting records show progress on Toyota Buffalo Hybrid Transaxle Plant.

    May 10, 2026Local reporting / county records

Procurement opportunities

2 tracked

  • Facility electrical distribution package80
    Power$7M66% procure
    Window closes Dec 31, 2026
  • Site civil & foundation work70
    Construction$7M56% procure
    Window closes Dec 31, 2026