StarPlus Energy Kokomo Gigafactories
Under ConstructionManufacturingStarPlus Energy (Stellantis / Samsung SDI)
Kokomo, Howard County, IN
Verification86/100
How corroborated this project is, 0 to 100, built from primary evidence: permits, utility interconnection filings, procurement notices and hiring activity. Higher means more independent sources confirm it.
Two Stellantis and Samsung SDI lithium-ion battery plants (33 and 34 GWh/year) representing about $5.7 billion in combined JV equity, separate from a $7.54 billion DOE loan supporting the build. Creates up to 2,800 jobs (1,400 per plant); production is targeted to begin in early 2027.
Investment$5.7B
Power demand400 MW
Jobs2,800
Serving utilityDuke Energy Indiana
Development stage
- Site Selection
- Pre-Construction
- Permitting
- Construction
Project timeline
Every detected update, newest first
No events recorded yet.
Procurement opportunities
3 tracked
- Dry-room HVAC & dehumidification84Cooling$120M68% procureWindow closes Nov 30, 2026
- Process automation integration82Services$140M70% procureWindow closes Dec 1, 2026
- Medium-voltage switchgear80Power$90M64% procureWindow closes Nov 15, 2026