How corroborated this project is, 0 to 100, built from primary evidence: permits, utility interconnection filings, procurement notices and hiring activity. Higher means more independent sources confirm it.
Blackstone-owned QTS advancing a $1.5 billion, 222MW multi-building campus adjacent to the hyperscaler cluster (NBC4). Interconnection queue position secured; local zoning conditions negotiated.
Investment$1.5B
Power demand222 MW
Jobs150
Serving utilityAEP Ohio
Development stage
- Site Selection
- Pre-Construction
- Permitting
- Construction
Project timeline
Every detected update, newest first
- Queue position confirmedUtility+4 evidence
Interconnection queue slot validated in the latest PJM cycle.
Jun 30, 2026PJM queue - Zoning conditions negotiatedPermit+1 evidence
Council attached noise and setback conditions to approval.
Apr 22, 2026City council minutes