Verification72/100

How corroborated this project is, 0 to 100, built from primary evidence: permits, utility interconnection filings, procurement notices and hiring activity. Higher means more independent sources confirm it.

ENTEK wet-process lithium-ion battery separator plant, a roughly $1.7 billion project (a $1.2 to $1.3 billion DOE loan plus a $200 million DOE grant and equity) creating about 635 operational jobs plus 763 construction jobs. Supplies a critical EV cell component underserved by US manufacturing.

Investment$1.7B
Power demand90 MW
Jobs640
Serving utilityDuke Energy Indiana

Development stage

  1. Site Selection
  2. Pre-Construction
  3. Permitting
  4. Construction

Project timeline

Every detected update, newest first

No events recorded yet.

Procurement opportunities

1 tracked

  • Solvent recovery & HVAC63
    Cooling$18M50% procure