Aligned Conesville AI Campus
Under ConstructionData CenterAligned Data Centers
Conesville, Coshocton County, OH
How corroborated this project is, 0 to 100, built from primary evidence: permits, utility interconnection filings, procurement notices and hiring activity. Higher means more independent sources confirm it.
Aligned's third Ohio campus, a 197-acre data-center development inside the Conesville Industrial Park next to the former AEP Conesville power plant (GlobeNewswire, July 2025). Aligned calls it a multi-billion-dollar, multi-building phased build but has not disclosed a specific dollar figure or MW rating; groundbreak was held in October 2025 and the first building already has a foundational customer, targeting mid-2026 initial capacity.
Development stage
- Site Selection
- Pre-Construction
- Permitting
- Construction
Project timeline
Every detected update, newest first
- Site plan submittedPermit+3 evidence
Full site plan filed with the municipality near Rickenbacker.
Jun 24, 2026City planning - Initial capacity delivery targeted mid-2026Announcement+4 evidence
Aligned targeting first go-live on the 197-acre Conesville AI campus with a foundational customer secured.
Jun 18, 2026Trade press - Project disclosedAnnouncement+2 evidence
Developer confirmed the ODC-01 build to local officials.
May 27, 2026Developer release
Procurement opportunities
3 tracked
- Physical-security systems integration63Security$14M47% procureWindow closes Feb 15, 2027
- Adiabatic cooling arrays61Cooling$28M46% procureWindow closes Jan 15, 2027
- Fire suppression & explosion protection52Supplier / OEM$6M42% procureWindow closes Jan 15, 2027